Home / Our business / Operations / Vele
Vele

-
Ownership
-
100%
-
Location
-
Limpopo Province, South Africa, 48km west of Musina
-
Infrastructure
-
-
Electricity supply secured from Eskom
-
Host properties have existing water uses which have been transferred to the mining operation
-
Accessible via existing tarred road network; initially the coal will be transported by truck to a rail siding (approximately 40km from Vele) until rail links have been completed
-
Extensive engagement with Transnet Freight Rail (TFR) to create capacity for domestic and export capacity
-
Resource
-
362.5Mt mineable tonnes in situ (MTIS) as classified under Joint Ore Reserves Committee (JORC)
-
Mining method
-
Opencast for 16 years, and underground mining thereafter
-
Product
-
Dual production; semi-soft coking with the option for either thermal export or middlings coal
-
Permit status
-
-
New Order Mining Right (NOMR) approved and Environmental Management Plan (EMP) executed in March 2010
-
Integrated Water Use Licence (IWUL) granted in May 2011 but has been suspended due to an appeal to the Water Tribunal submitted by a non-governmental organisation (NGO) coalition in July 2011 – the minister lifted the suspension of the licence on 19 October 2011
-
Compliance notice lifted on 5 July 2011
-
Key highlights
-
-
The mine reached an important milestone, achieving 1,000 fatality-free production shifts, at the beginning of December 2012.
-
A plant expansion at Vele is planned to process the discard from the semi-soft coking coal product through a second-stage wash process to produce either an export-grade thermal coal or an Eskom middlings. This expansion will enable the simultaneous production of products, increased qualities and yields through the improvement of recoveries.
-
Phase 1 will allow for the dewatering of the ultra-fines product by installing filter presses; eliminating the need for the temporary slurry pond and Phase 2 incudes the installation of a permanent front-end crushing facility and dual-product thermal and coking-coal plant module.
VELE PROFILE
22 NOVEMBER 2016
CREATING SUSTAINABLE VALUE THROUGH MINING FOR ALL STAKEHOLDERS
-
Section 24G
-
-
EMC Annual Report 2012
-